Courtenay’s Greenwood Trunk Sewer Main Complete

Friday, June 3, 2022 at 9:02 AM

By Meg Polson

The Greenwood Trunk sewer main in East Courtenay is now complete.

The Greenwood Trunk sewer main in East Courtenay is now complete.

It was the top priority in the City of Courtenay's Sewer Master Plan.  The project has increased sewer capacity in East Courtenay for current and anticipated development. The project includes new sanitary sewer mains off Anderton Road and a new sewer pump station, redirecting substantial sewage flows away from the Courtenay lift station and connecting to an existing section of the Greenwood Trunk Sewer constructed by the Comox Valley Regional District in 2017.

Courtenay’s Greenwood Trunk includes 600 metres of gravel roadway, 3.2 kilometres of pipe, and other supporting works, and will allow three smaller lift stations to be decommissioned.

Originally budgeted for $4.1 million, the project has required two budget reallocations to address the groundwater issues, bringing the total cost to $6.95 million. The City of Courtenay is pursuing all options for cost recovery to offset the additional expense.

$1 million for the project has been provided through Community Works (Gas Tax) Funds.