Crews continue to remove boulders as part of the rock-scaling work being done at Angel Rock.
Today’s closure runs from 8:30 a.m. until 9 p.m. Work last Thursday saw the removal of five large boulders – the largest of which was approximately 1.2 cubic meters – and 10 truckloads of rock debris from the area. Outside of today’s full-day closure, the highway will continue to be closed for two periods daily until opening, from 9 a.m. until 11:30 a.m., and from 1:30 p.m. until 5 p.m., until the work is completed. There will be no closures overnight or on weekends. For up-to-date information about road conditions, visit: https://drivebc.ca
Wildfire Update
Partial Road Closure on Hilchey Road for Work on Bike Lanes
Harrogate Road and Erickson Road Intersection Closure Extended to September 4th
Comox Valley RCMP warns about fake social media posts
RibFest at Village Park August 21-23